Question
A contractor had mistakenly erected 20 metres extra fencing. He demands that I pay for this extra fencing which I had not ordered. What am I supposed to do?
Answer
The contractor who had mistakenly erected an extra 20 metres of fencing may not hold you responsible. Either he may remove the fencing or come to some compromise with you if you wish to retain the fencing. The second transaction may be concluded by mutual agreement. However, if the parties cannot agree to a price, then the contractor should remove his material.
Download issue PDF EPUB
- Source
- themajlis.co.za
- Published in
- The Majlis Vol 24 No 04
- PDF page
- 5
Verbatim verified against the source PDF
Appears under IMASA IS A JAHIL MUDHIL. This heading is the nearest headline at or before the page and is approximate. Do not cite it alone.