Question
If I give a quote for work on an old building, and I encounter obstacles and I overcome them by making changes, can I meet to the needs of what's to be done? In the process I incur more costs. Is it right or wrong to claim the extra costs? For example, I need to build two toilets and two showers but realised that the floor needs to be raised to meet the drainage outside drain, or I tile the showers and toilets although I did not mention this in the original quote. Can I ask for the extra cost?
Answer
It is not permissible to demand the extra cost if the changes and alterations were undertaken without the approval of the employer. If you unilaterally incur more costs, you will be liable for it. The original quote cannot be increased without the approval of the person who has employed you.
- Source
- themajlis.co.za
- Published in
- The Majlis Vol 25 No 08
- PDF page
- 2
Verbatim verified against the source PDF
Appears under SCHOOL IMMORALITY |. This heading is the nearest headline at or before the page and is approximate. Do not cite it alone.